Life of Mine: where the value is won or lost
A copper mine is decided over many years, paid for up front and judged decades later. The figures from the film show where its value is set, from discovery to closure.
Every figure is taken from the film's sourced cards. Watch the film.
Discovery to first production
On average, 16 years. For the newest mines, closer to 18.
Across 232 assets brought into production from 1990 to 2025. Where a feasibility study is complete but the mine is not yet built, the wait stretches to nearly 30 years, largely in permitting.
Sources: S&P Global Market Intelligence, 8 July 2026 (16-year average; nearly 30 years for non-operating assets with completed feasibility studies) and 10 April 2024 (by start year; gold, copper, nickel and lithium). Bar scale 0 to 30 years.
Discoveries that became mines
Fewer than half of all discoveries have become mines
Of about 3,500 non-ferrous discoveries made from 1950 to 2013, 45% had become mines by 2014. For copper, 39%. The rate rises as later finds are developed; MinEx expects final rates about 15 points higher.
Sources: R. Schodde, MinEx Consulting, PDAC Mineral Economics session, March 2014; copper rate as reported by Mining News North, 25 May 2014.
Direct capital cost, US$ million
The pit is 17% of direct cost. The plant and the infrastructure are the rest.
A High Andes copper-gold project at about 4,000 to 4,900 metres. Direct cost US$1,729m; with indirects, contingency and owner's costs, US$3,091m. Power alone arrives on a 252 km, 220 kV line.
Sources: Josemaria Resources, Feasibility Study, October 2020, Table 9; Lundin Mining (elevation). The 17% share is a ZMK calculation. Josemaria now sits in Vicuña Corp, a Lundin Mining and BHP joint arrangement; the study figures are historical.
Capital cost: estimate against outcome
As built, capital came in 25% above the bankable feasibility estimate
The average across 63 mining and smelting projects over four decades. A valuation that takes the feasibility number at face value inherits the gap.
+25% on average
Source: J. Bertisen and G. A. Davis, "Bias and Error in Mine Project Capital Cost Estimation", Society for Mining, Metallurgy & Exploration, 2007. Index: feasibility estimate = 100.
Billions of tonnes for kilograms of metal
The plan moves about 2 billion tonnes to recover 2.6 kg of copper from each tonne of ore
Everything else, about 997 kg of every tonne, goes to the tailings facility.
Source: Josemaria Resources, Feasibility Study, October 2020. Total tonnage and metal per tonne are ZMK calculations from the study's grades and recoveries.
Chile: average ore grade at concentrators
Grade has halved since 2000. The same copper now needs twice the rock.
From 1.38% copper in 2000 to 0.69% in 2025. More rock means more energy, water and tailings for each tonne of metal, and older mines go deeper or underground to stay open.
Source: C. Cifuentes González, CESCO, Producción de cobre en Chile 2000-2026, 2026, Table 2, from the Cochilco statistical yearbook. "Twice the rock" is a ZMK calculation (1.38 / 0.69).
Life of mine, US$ billion, undiscounted
The state takes US$2.7bn in royalties and taxes. The owners keep US$6.4bn.
On the study's base case of US$3.00/lb copper and US$1,500/oz gold. Operating costs are the largest call on revenue; closure is the smallest line, and the last to be paid.
Source: Josemaria Resources, Feasibility Study, October 2020, Tables 1, 9, 10, 11 and 13, in a ZMK arrangement. Base case Cu US$3.00/lb, Au US$1,500/oz, Ag US$18/oz.
Closure and rehabilitation provisions
Rio Tinto and BHP carry US$17.8bn and US$11.6bn of closure provisions
Rio Tinto's provision is US$17.8bn at present value, US$25.9bn undiscounted. Since 2020, tailings facilities are also measured against a global standard of 77 auditable requirements.
GISTM, August 2020: 6 topic areas, 15 principles, 77 auditable requirements
Sources: Rio Tinto, Form 20-F FY2025; BHP, Form 20-F FY2026; UNEP, ICMM and PRI, Global Industry Standard on Tailings Management, 5 August 2020. Bar scale 0 to US$20bn.
What decides the outcome
Three numbers a board should test before it commits capital
- The calendar. A 16-year average lead time, and nearly 30 once permitting stalls. Every year of delay defers all of the cash.
- The capital estimate. Feasibility estimates have run 25% light on average. The overrun lands before the first tonne is sold.
- The closure bill. Small in the cash flow, large on the balance sheet, and paid when the mine no longer earns.
A mine plan can be tested against what comparable projects actually delivered. That test is cheapest before the decision.
Cerro Estrato, the mine in the film, is fictional. Josemaria figures are from a 2020 feasibility study and are historical. ZMK Advisory holds no position in, and has no engagement with, any company named. Not investment research.