Life of Mine.
From first core to final cover: how a copper mine is found, permitted, built, run and closed, and where its value is won or lost.
A mine is decided in a few years, paid for up front, and judged decades later. The value is won or lost long before the first tonne and long after the last.
- 16 yearsthe average from discovery to first production, across 232 mines brought into production since 1990.1
- 45%of the non-ferrous discoveries made from 1950 to 2013 had become mines by 2014.2
- 25%the average overrun of as-built capital against the bankable feasibility estimate, across 63 mining and smelting projects.3
- About 2 billion tonnesof ore and waste moved over a 19-year mine plan for a large High Andes copper project.4
- Halvedthe average ore grade at Chile’s copper concentrators, from 1.38% in 2000 to 0.69% in 2025.5
8 min Nine details in this film don't hold up.
Only someone who has worked on a mine will catch them all. Eight Strata marks are hidden in the film too. Count both, then check your answers.
Watch the film first. The key has every detail and every mark with its timecode and a still.
Where a mine's value is won or lost.
Ten slides, one sourced chart each: the lead time, the capital, the grade, the cash and the closure bill.
Every figure carries its source and date, as in the film.
A valuation inherits the lead time, the overrun and the closure bill.
Each one is set years before it shows in the numbers. We test a mine plan against what comparable projects actually delivered before a board commits capital to it.
If the film touches an asset or a decision on your desk, write to us directly.
- S&P Global Market Intelligence (P. Manalo), “From Discovery to Delay: Mine Permitting Stretches Project Timelines”, 8 July 2026. Link
- R. Schodde, MinEx Consulting, “Key issues affecting the time delay between discovery and development: is it getting harder and longer?”, PDAC Mineral Economics session, Toronto, March 2014. Link
- J. Bertisen and G. A. Davis, “Bias and Error in Mine Project Capital Cost Estimation”, Society for Mining, Metallurgy & Exploration, 2007. Link
- Josemaria Resources Inc., Feasibility Study news release, 19 October 2020 (ore 1,012 Mt, waste 992 Mt, 19-year mine life; total is a ZMK calculation). Link
- C. Cifuentes González, Centro de Estudios del Cobre y la Minería (CESCO), Producción de cobre en Chile 2000-2026, 2026, Table 2, from the Cochilco statistical yearbook. Link
Links accessed 27 Nov 2026.