Analysis  /  Make-or-Buy Series  /  West Africa
Analysis · West Africa · Steel

$8bn spent.
Not a tonne of steel made.

Forty-seven years and more than $8bn after construction began, Nigeria’s Ajaokuta complex has never lit its blast furnace. That record is not an anomaly to explain away. It is the base rate every West African integrated-steel build case should price.

ZMK Advisory Research 08 July 2026 · updated 4 October 2026 9 min read Facts-First Analysis
Key points

After 47 years and more than $8bn, Ajaokuta’s own record is the base rate, and it says buy the steel and redirect the capital.

  1. 01Ajaokuta was due in 1986 and reported 98% complete in 1994. Its blast furnace has never run.Published estimates put the spend at more than $8bn, and some at $10bn.
  2. 02Every new appropriation has assumed the plant will be finished.The build case treats the probability of completion as one. The plant’s own record says it is not.
  3. 03Priced on its completion odds, a domestic tonne costs far more than an imported one.Its cost is the nameplate price divided by the odds it ever arrives, before the cost of the capital tied up in it.
  4. 04The next dollar should wait for a financed, contracted commissioning date.Neither the 2024 agreement with Tyazhpromexport nor the 2026 talks on a $2bn Chinese-backed plan has produced one.
Ajaokuta, 1979 to 2026
Every milestone except the one that matters: a commissioning date.
  1. 1979Construction begins. The Soviet state firm Tyazhpromexport is the builder. 2, 5
  2. 1986Completion date scheduled under the original contract. 3
  3. 1994Plant reported 98% complete. 2
  4. 2004Plant conceded to Global Infrastructure Holdings. 2
  5. 2008Concession terminated by the Yar’Adua government. 2, 4
  6. 2018Spend put at more than $8bn; the plant has never produced steel. 1
  7. 2022Nigeria agrees to pay $496m to settle a $5.3bn claim over the concession. 4
  8. 2024New MoU with Tyazhpromexport to complete the plant. No financing or date stated. 5
  9. 2026Talks on a $2bn Chinese-backed rehabilitation plan. 6
Sources are numbered and listed at the end of this note.
01 · Context

Ninety-eight per cent complete in 1994, and still not commissioned.

Construction began in 1979, with the Soviet state firm Tyazhpromexport as builder 2, and the contract scheduled completion for 1986 3. By 1994 the plant was reported 98% complete 2. Since then it has passed through a concession, the termination of that concession, and a $496m settlement 4. The rolling mills were built ahead of the steelworks and have run on imported billet. The blast furnace, which is what would make this a steel plant rather than a finishing shop, has never been turned on 3.

Published estimates put the spend at more than $8bn 1, and some at $10bn 2. The figure that matters is not any single year’s budget line. It is the total the sunk-cost fallacy has protected for forty-seven years.

47
Years since construction began
$8bn+
Spent, published estimates
0
Days the blast furnace has run
02 · Framework

This was always a make-or-buy question, priced as a nation-building one.

Strip the symbolism and the decision reduces to a single comparison: the delivered cost of a domestically produced tonne of steel against the delivered cost of an imported one, discounted by the probability the domestic tonne ever arrives. For forty-seven years, that third term, the probability of completion, has been treated as one. It is not.

The bear case the consensus is missing is rarely a new fact. It is the base rate the room has agreed to stop counting.

Ajaokuta’s own record is the base rate: scheduled for 1986, 98% complete in 1994, and not commissioned in 2026. The build case survives only when each new appropriation is underwritten as if that record did not exist, as if this tranche, unlike every tranche before it, closes the gap.

03 · Quantified Impact

The disciplined move is to buy the steel and redirect the build.

Once completion probability is priced honestly, the domestic tonne is not marginally more expensive. It costs its nameplate price divided by its odds of ever arriving, before the opportunity cost of the capital held hostage to it. For an operator or a sovereign principal weighing exposure to the complex, the conclusion follows from the arithmetic, not from sentiment about industrial sovereignty.

What we would tell the committee

Treat the sunk $8bn as sunk. Underwrite the next dollar on its own completion odds. Those odds say import the billet, redirect the capital, and revisit only against a financed, contracted commissioning date that has never yet existed.

The 2024 MoU with Tyazhpromexport 5 and the 2026 talks on a $2bn Chinese-backed plan 6 are the latest attempts. Neither has yet produced that date. None of this requires a view on steel demand, on the naira, or on the political will of any government. It requires only that the completion term be set to its observed value rather than to one. That is the whole of the analysis, and it is the part the story leaves out.

Make-or-Buy Series The number, then the narrative.
Sources

Each figure in this note traces to one of the sources below.

  1. Al Jazeera, “Nigeria: Steel factory will open after 40 years”, 16 June 2018. Spend of more than $8bn; no steel produced.
  2. The Guardian (Nigeria), “Ajaokuta Steel Plant: Like refineries, a story retold, promises unkept”, 13 January 2023. Tyazhpromexport as builder; 98% complete in 1994; concession 2004 and termination 2008; estimates of $8bn to $10bn.
  3. Nairametrics, “Why Ajaokuta Steel Company cannot produce steel”, 23 August 2018. Completion scheduled for 1986; blast furnace never turned on; rolling mills run on imported billet.
  4. Bloomberg, “Nigeria settles $5.3 billion claim from Indian-owned steel firms”, September 2022. Agreement to pay $496m; concession revoked in 2008.
  5. News Agency of Nigeria, “FG signs MoU with Russian firm to complete Ajaokuta steel coy”, 21 September 2024.
  6. BusinessDay, “42-year-old Ajaokuta plant set for reboot with $2bn Chinese-backed plan”, 2 March 2026.

Updated 4 October 2026: headline and figures aligned to published sources; timeline replaces an unsourced spend curve; unsourced cost comparison removed; source list added.

Related field notes

All Field Notes →